$16m DRYING KILN UPGRADE COMPLETE AT JUBILEE

FOREST manager OneFortyOne’s second continuous drying kiln is now online, completing a $16 million capital investment project at the Jubilee sawmill site in Mount Gambier, SA.

Sawmill general manager Paul Hartung said the kilns were working well and had increased site capacity while improving the quality of the timber dried.

“The CDK’s are powered by our own sawdust and wood waste offcuts, and their efficient design is using less energy to process more timber compared to our old batch kilns,” Mr Hartung said.

“With the old batch kiln we put 150 cub m of timber in at a time, drying it at up to 160 deg. to achieve a moisture level down to 12%,” he said. “These high temperatures can stress the timber.

“With the CDK, we load the timber to move through the drying process. With the efficiencies of shared energy and temperature control, the new kilns have a maximum temperature of 130 deg. which is a lot less aggressive on the timber as it dries.”

Two of four older batch kilns will be reconditioned and will remain on site to provide added flexibility and for backup when the new kilns are offline for maintenance.

The upgrade project is part of a greater Jubilee-wide modernisation program, which has included state-of-the-art sawing equipment upgrades, through to the addition of a robotic pack wrap and strapping machine.

“The upgrades and new equipment on site are creating better and safer working environments for everyone,” Mr Hartung said.

“The team is also getting the opportunity to gain new skills, work with the latest technology, and enjoy a safer and more modern workplace.”